How to Lay Pavers: Step-by-Step Patio Guide

A paver patio is mostly about the base. If you dig deep enough, compact the gravel in thin layers, and screed a flat sand bed, the pavers themselves go down fast. This guide walks through each step with the numbers that matter: excavation depth, base thickness, slope, sand, and joint fill.

Get your materials list first. The free paver calculator works out pavers, base gravel, bedding sand, joint sand, edging, and fabric for your patio.

Related: paver patio cost

What you need

Tools

  • Shovels, a flat spade, and a wheelbarrow
  • Plate compactor (rent one)
  • Stakes, mason’s string, and a line level
  • 4 ft level and a long straight board for screeding
  • Two 1 in pipes (conduit works) to use as screed rails
  • Rubber mallet, push broom, and leaf blower
  • Wet saw or masonry blade for cuts, or a paver splitter for straight cuts

Materials

  • Pavers, plus 5 to 10% extra for cuts
  • Crushed gravel base (3/4 in minus or paver base, with fines so it packs)
  • Coarse concrete sand for the bedding layer (not play sand or mason’s sand)
  • Geotextile fabric, strongly recommended on clay or soft soil
  • Edge restraint and 10 in spikes
  • Polymeric joint sand

Step 1: Plan, call 811, and set the slope

  • Call 811 a few days before you dig.
  • Mark the patio outline with paint or string. Square corners with the 3-4-5 method.
  • Plan for the patio to slope away from the house at about 1/8 to 1/4 in per foot. A 12 ft patio drops about 1.5 to 3 in from the house side to the far edge.
  • Set string lines at the finished paver height, with the slope built in. Measure every depth from these lines.

Step 2: Excavate

  • Depth: paver thickness + 1 in of sand + the gravel base. For a 2-3/8 in paver on a 4 in base, dig about 7-3/8 in below finished height.
  • Base depth: about 4 in for a patio or walkway in mild climates, and 6 in in freeze-thaw areas or on soft soil. Driveways need more.
  • Width: dig 6 to 12 in past the paver edge on all sides so the base supports the edge restraint.
  • Compact the soil at the bottom with the plate compactor. Dig out soft spots and fill them with base.

Step 3: Lay fabric and build the base

  • Lay geotextile fabric over the soil, overlapping seams about 12 in.
  • Spread the gravel in 2 to 3 in layers (lifts). Dampen each layer lightly and compact it with at least two passes before adding the next.
  • Pay extra attention to edges and corners, where base tends to stay loose.
  • The finished base should follow your slope and be flat within about 3/8 in under a 10 ft straight board.

Step 4: Screed the sand

  • Lay the two 1 in pipes on the base about 4 to 6 ft apart.
  • Fill between them with sand and pull a straight board across the pipes to strike a smooth 1 in layer.
  • Remove the pipes, fill the grooves with sand, and smooth them with a trowel.
  • Do not walk on or compact the screeded sand. Screed only what you can cover with pavers that session.

Step 5: Lay the pavers

  • Start at a straight, fixed edge such as the house or a 90 degree corner, and work outward.
  • Set each paver straight down instead of sliding it, so the sand bed stays flat. Keep joints consistent, about 1/8 in.
  • Kneel on the pavers you have already laid, not the sand.
  • Check your string lines every few rows to keep the pattern straight.
  • Lay all the full pavers first, then mark and cut the edge pieces. Avoid slivers smaller than about a third of a paver at the edges.

Step 6: Install the edge restraint

  • Set the edge restraint tight against the outside pavers, on the gravel base.
  • Drive spikes about every 12 in. On curves, cut the back flange so the restraint can bend.
  • Backfill behind the restraint with soil and sod or mulch.

Step 7: Compact and fill the joints

  • Sweep the surface clean, then make two passes with the plate compactor to seat the pavers into the sand. Use a pad under the plate for textured or tumbled pavers.
  • Sweep polymeric sand diagonally across the joints until they are full, then compact again and top off any joints that settle.
  • Blow all loose sand off the paver faces before wetting. Leftover sand can leave a haze.
  • Mist with a hose following the bag’s directions, and keep traffic off for about 24 hours.

How much does it cost to lay pavers yourself?

For a 12 x 16 ft patio with 6 x 9 in concrete pavers and a 4 in base, the paver calculator lists 538 pavers, 4.5 tons of base gravel, 1 ton of sand, 4 bags of polymeric sand, edging, fabric, and delivery, for about $1,275 in materials. Add a plate compactor rental and a saw. A pro would typically charge about $1,540 to $4,610 for the same patio. See paver patio cost for more.

How long does it take?

Two people can usually finish a 12 x 16 patio in a long weekend. Digging out and compacting the base takes the most time, often more than half the job.

Common mistakes to avoid

  • Too little base, or base dumped in one thick layer instead of compacted lifts
  • No slope, which leaves puddles against the house
  • Using sand as the leveling layer for low spots in the base (fix low spots with gravel, not extra sand)
  • Skipping the edge restraint, so pavers creep apart
  • Leaving sand on the surface when wetting polymeric sand

FAQ

How deep should I dig for pavers?

Add the paver thickness, 1 in of sand, and 4 to 6 in of base. That is usually about 7 to 10 in below finished height for a patio.

Can I lay pavers on dirt?

Not if you want them to stay flat. Without a compacted gravel base, pavers settle, heave, and shift within a season or two.

How much sand do I need under pavers?

A 1 in layer. That is roughly 1 ton per 200 sq ft. The paver calculator figures it for your size.

Do I need polymeric sand?

It is not required, but it hardens in the joints and resists weeds, ants, and washout far better than plain sand.