How to Build a Retaining Wall: Step-by-Step Guide

A short block retaining wall is a manageable DIY project if you get three things right: a compacted gravel base, a buried first course, and drainage behind the wall. This guide covers building a dry-stacked interlocking block wall up to about 3 ft tall, with the numbers that matter at each step. Taller walls, or walls holding up a driveway or building, need an engineer.

Get your materials list first. The free retaining wall calculator figures blocks, caps, base gravel, drainage stone, pipe, and fabric for your wall.

Related: retaining wall cost

What you need

Tools

  • Shovels, a flat spade, and a wheelbarrow
  • Plate compactor or hand tamper
  • Stakes, mason’s string, and a line level
  • 2 ft and 4 ft levels
  • Rubber mallet or dead-blow hammer
  • Saw with a masonry blade, or a hammer and chisel for splitting block
  • Caulk gun for cap adhesive

Materials

  • Interlocking retaining wall block and caps
  • Crushed gravel base (3/4 in minus with fines)
  • Clean drainage stone (3/4 in or #57, no fines)
  • 4 in perforated drain pipe
  • Filter fabric (geotextile)
  • Masonry or block adhesive for the caps

Step 1: Check the rules and plan

  • Ask your town if you need a permit. Many require one, and an engineered design, for walls over 4 ft. Some also regulate walls near property lines.
  • Check the block maker’s maximum height for an unreinforced wall. Taller walls need geogrid layers tied into the soil behind.
  • Call 811 before digging.
  • Plan where the water will go. The drain pipe needs a place to drain to, at a lower point or out the end of the wall.

Step 2: Dig the base trench

  • Mark the wall line with string or paint.
  • Width: about 12 in wider than the block depth, so the base extends at least 6 in in front of and behind the first course. For a 12 in deep block, dig about 24 in wide.
  • Depth: enough for 6 in of compacted base, plus the buried part of the first course. Bury at least 6 in of block, or about 1 in for every 8 in of wall height, whichever is more.
  • Dig back into the hill far enough to leave room for at least 12 in of drainage stone behind the block.
  • Compact the soil at the bottom of the trench.

Step 3: Build the leveling pad

  • Spread the gravel base in 2 to 3 in layers, dampen lightly, and compact each one.
  • Build it to at least 6 in thick after compaction.
  • Level the top front to back and side to side. If the ground slopes along the wall, step the base up in increments equal to one block height.

Step 4: Set the first course

  • Start at the lowest point of the wall, or at a corner.
  • Run a string line along the back of the blocks to keep them straight.
  • Set each block on the base and level it side to side and front to back, tapping with a mallet. Check the course every few blocks.
  • Take your time here. Every error in the first course shows up higher in the wall.

Step 5: Add drainage

  • Lay the perforated drain pipe behind the first course at the bottom of the trench, running to your outlet. Long walls may need outlets through the wall face about every 50 ft.
  • Line the back of the excavation with filter fabric so soil does not clog the stone.
  • Fill at least 12 in behind the block with clean drainage stone, and fill the block cores if they are hollow.
  • Backfill in front of the first course with soil to hold it in place.

Step 6: Stack the courses

  • Sweep the top of each course clean so the next one sits flat.
  • Stagger the joints so each block spans the joint below, like brick.
  • Pull each block forward so its lip or pins lock into the course below. This builds in the backward lean (setback) that helps the wall resist soil pressure.
  • After each course, add drainage stone behind the block and compact the soil behind the stone. Keep heavy compactors a few feet back from the wall.
  • Cut blocks as needed to keep joints staggered at the ends and corners.

Step 7: Cap and finish

  • Fold the filter fabric over the top of the drainage stone.
  • Cover the last 6 to 8 in behind the wall with compacted native soil, so surface water does not run straight into the drainage zone.
  • Glue the caps to the top course with block adhesive, overhanging slightly if you like.
  • Grade the top so water runs away from the wall, not over it.

How much does it cost to build a retaining wall yourself?

For a 30 ft long, 3 ft tall wall in medium block, the retaining wall calculator lists 170 blocks, 24 caps, 2 tons of base gravel, 5.5 tons of drainage stone, drain pipe, fabric, adhesive, and delivery, for about $1,650 in materials. A contractor would typically charge about $1,800 to $4,500 for the same wall. See retaining wall cost for prices by material.

How long does it take?

Two people can usually build a 30 ft wall, 3 ft tall, over two weekends. Digging the trench and setting the first course take the most time. A medium wall block can weigh 30 lb or more, so line up help.

Common mistakes to avoid

  • Setting the first course on dirt or a thin, loose base
  • Not burying the first course
  • Backfilling with soil instead of drainage stone, or skipping the drain pipe
  • Building taller than the block’s rated height without geogrid or an engineer
  • Stacking blocks with joints lined up
  • Letting downspouts or a slope dump water right behind the wall

FAQ

How tall can I build a retaining wall myself?

Most block makers and towns treat walls under about 3 to 4 ft as DIY friendly. Check your block’s maximum unreinforced height and local permit rules before going taller.

Do retaining walls need drainage?

Yes. Water pressure behind a wall is a leading cause of failure. Use at least 12 in of clean stone behind the block and a perforated drain pipe at the bottom.

How deep should the base be?

At least 6 in of compacted gravel, plus a buried first course of at least 6 in.

Do I need adhesive between blocks?

Interlocking blocks hold by weight and their lips or pins. Adhesive is usually used only on the caps.